| Country |
Contract |
Brief |
Value |
Employer |
Duration |
| Ghana |
Urban Roads, Accra |
31.8 km of rehabilitation and new dual carriage road, executed in 2 phases |
$26,774,000 |
Ministry of Roads and Transport |
11.92-02.99 |
| Ghana |
Rehabilitation of Trunk Roads |
Rehabilitation and maintenance of 150 km Trunk Roads in Brong-Ahato Region executed in 2 phases |
$25,320,000 |
Ghana Highwqaws Authority |
05.93-01.00 |
| Ghana |
Takoradi Urban Roads |
Rehabilitation of Urban Roads in Takoradi Township |
$12,600,000 |
Ministry of Roads and Transport |
10.95-10.97 |
| Ghana |
Rehabilitation of Trunk Roads Lots 3, 4 & 5 |
Rehabilitation of 312 km trunk roads |
$10,600,000 |
Ghana Highways Authority |
09.98-12.99 |
| Ghana |
Rehabilitation of Takoradi - Agona Junction Road |
Rehabilitation and reconstruction including construction of 4 km urban dual carriage way, total length 32 km. |
$20,216,000 |
Royal Danish Ministry of Foreign Affairs - DANIDA |
11.00-11.02 |
| Ghana |
Takoradi Thermal Power Plant - TK1, civil works |
Civil Engineering works& infrastructure for a 200MW gas turbines power plant |
$24,220,000 |
Stone & Webster Int. Corp. |
04.96-05.98 |
| Ghana |
Odaw Drainage Channel, Lot 2. Accra. |
Main Urban Drainage Channel & Bridge |
€8,931,000 |
Ministry of Local Government and Rural Development |
05.03-06.05 |
| Ghana |
Anyinam-Konongo Section I of Anyinam-Kumasi Road, Asphalt Concrete Overlay. |
Road Construction |
$17,259,000 |
Ministry of Road &Transportation Ghana Highways Authority |
01.03-05.05 |
| Ghana |
Reconstruction of the Tetteh Quarshie Circle to Mamfe Road. Contract 1: Construction of Tette Quarshie Interchange. |
Urban Road & Bridge Constrruction |
$9,588,000 |
Ministry of Road &Transportation Ghana Highways Authority |
01.03-05.05 |
| Ghana |
Road Rehabilitation and Traffic Management works in Secondi-Takoradi. |
Road Rehabilitation & Traffic Management works |
$10,484,000 |
Ministry of Road &Transportation Ghana Highways Authority |
05.03-05.05 |
| Nigeria |
Nicon Administration Headquarters Building, Abuja |
8,500 sq.m office building + 6,500 sq.m underground parking. Completion delayed due to Employer's economic constraints |
$18,000,000 |
Nicon Insurance Corporation |
2004-02.01 |
| Nigeria |
Jos Bukuru Water Supply Project |
A complete water scheme to serve 300,000 people including Treatment Plant, Mains, Concrete reservoirs, and distribution |
$12,460,000 |
Plateau State Water Board (African Development Bank Finance) |
03.95-11.00 |
| Nigeria |
Ibadan - Ife Road Dualization |
Adding 2 lanes to an existing 77.4 km road and rehabilitation of the existing road |
$97,029,000 |
Federal Ministry of Works |
12.95-05.99 |
| Nigeria |
Kwoi Water Supply Scheme |
Water Treatment Plant, Distribution Mains and Reservoir |
$16,100,000 |
Kaduna State Water Board |
08.96-11.98 |
| Nigeria |
Benin Asaba Road Dualization Section I |
Adding 2 lanes to an existing 39.6 km road and rehabilitation of the existing road |
$37,700,000 |
Federal Ministry of Works |
03.93-10.01 (work stopped between 1995 and 1997) |
| Nigeria |
Benin Asaba Road Dualization Section II |
Adding 2 lanes to an existing 43.9 km road and rehabilitation of the existing road |
$28,750,000 |
Federal Ministry of Works |
02.00-02.02 |
| Nigeria |
Benin Asaba Road Dualization Section III |
Adding 2 lanes to an existing 45.9 km road and rehabilitation of the existing road. + 6 Km of new alignment |
$34,434,000 |
Federal Ministry of Works |
04.00-05.02 |
| Nigeria |
Ife Ilesha Road Dualization |
Adding 2 lanes to an existing 49.5 km road and rehabilitation of the existing road |
$57,760,000 |
Federal Ministry of Works |
04.00-05.02 |
| Nigeria |
Mallam Aminu Kano International Airport Main Runway Rehabilitation |
Rehabilitation of existing Runway |
$10,380,000 |
Federal Airports Authority |
04.02-02.03 |
| Guatemala |
Rehabilitaci?n of road CA-1 Occidente, Section Los Encuentros-Cuatro Caminos |
Rehabilitation & reconstruction of 60.85 km road |
$12,814,000 |
Ministerio de Comunicaciones, Infraestructura Y Vivienda |
11.95-02.98 |
| Guatemala |
Construction of La Casaca-El Naranjo Road, Peten |
Construction of 80 km road |
$13,644,000 |
Ministerio de Comunicaciones, Infraestructura Y Vivienda |
09.97-12.99 |
| Guatemala |
CA-13 Sec, San Luis-Poptun-Flores Road |
105.7 km Road rehabilitation, + 8 bridges |
$40,939,000 |
Ministerio de Comunicaciones, Infraestructura Y Vivienda |
05.97-06.00 |
| Guatemala |
Rehabilitation of CA-14 Prolongation Coban-Chisec-Xuctzul Road |
77.9 km Road rehabilitation & reconstruction, + 1 bridge |
$13,302,000 |
Ministerio de Comunicaciones, Infraestructura Y Vivienda |
01.00-09.02 |
| Guatemala |
La Libertad - San Diego Road |
Rehabilitation & construction of 53 km road |
$11,325,000 |
Ministerio de Comunicaciones, Infraestructura Y Vivienda |
10.00-10.02 |
| Guatemala |
La Cumbre-Purulha Road |
Trunk Roads Construction |
$17,288,000 |
Ministerio de Communicacionas, Transporte Y Obras Publicas |
01.03-06.05 |
| Guatemala |
El Canada Hydro Electric Power Plant |
45 MW Hydro electric power plant |
$41,300,000 |
Energia Global Internacional Ltd.s |
03.02-04.04 |
| Guatemala |
Flores y San Benito Water & Drainage Works. |
Urban Water & Sewerage Construction |
$10,020,000 |
INFOM-Instituto de Fomento Municipal |
05.04-07.05 |
| Ivory Coast |
Administration Center, Abidjan Harbour |
7 story office building |
$4,950,000 |
Porte Autonome d'Abidjan |
01.96-06.98 |
| Ivory Coast |
Conference Hall Daoukro |
6,000 sq.m conference complex |
$16,100,000 |
Ministry of Construction & Urbanization |
09.96-05.99 |
| Ivory Coast |
Presidentil Residence, Cocody, Abidjan |
Construction of Presidential Building Complex |
$22,800,000 |
The President of Cote d'Ivoire, through BNETD |
10.96-05.99 |
| Ivory Coast |
Daoukro- Aprompronou Road |
Road rehabilitation and construction |
$12,730,000 |
Ministry of Infrastructure & Economics |
10.96-10.98 |
| Ivory Coast |
Atlantic Bank Office BACI Building, Abidjan |
Construction of 9 story office building |
$6,700,000 |
S.C.I Nogues through S.C.O Afrique |
02.98-08.99 |
| Colombia |
Funza & Mosquera Towns - Sewage System |
pumping station, treatment plant & sewers |
$11,500,000 |
Corporacion Autonoma Regional de Cundinamarca |
11.95-02.98 |
| Uganda |
Road Development Program Phase I, Nebbi-Arua Road Upgrading |
Rehabilitation of 76.3 km road |
$24,180,000 |
Ministry of Works, Housing & Communication, Road Agency Formation Unit |
08.01-11.03 |
| Benin Republic |
Main Concrete Drainage - Cotonou |
600 m Drainage Channel, average width 12 m, constructed on 300,000 cu.m sand fill |
$4,580,000 |
AGETUR - Urban Works Agency |
10.01-01.03 |
| Benin Republic |
Access to the 3rd Bridge |
5 km dula carriageway road |
$21,000,000 |
Ministry of Works |
07.03-02.05 |
| Togo |
Atakpame-Blitta Road Rehabilitation |
Rehabilitation of 102 km road |
$19,300,000 |
Ministry of Mines, Energy, Ports & Telecommunication |
04.98-05.99 |
| Republic of Congo |
Point Noire Airport |
Reconstruction of runway |
$6,600,000 |
LR Avionics Technologies, for the Ministry of Transportation and Aviation |
02.01-11.02 |
| El Salvador |
San Martin-San Rafael Cedros Highway |
Reconstruction & construction of dual carriage way Highway |
$47,715,892 |
Ministerio de Obras Publicas, Transporte, Viciande y Desarrolo Urbano |
10.01-04.04 |